Posted By Wendy Weiman 05-06-2019 12:07 PM
Found In Egroup: Environment, Coasts, Oceans, & Infrastructure
\ view thread
Ian - that was what we were anticipating (13-15% of construction costs for Phase 2). Do you have a reference that we could cite. We need to justify the cost and a reference stating this as an industry standard would be helpful. Thank you in advance! ------------------------------ Wendy Weiman, ...
Posted By Wendy Weiman 05-03-2019 11:58 AM
Found In Egroup: Environment, Coasts, Oceans, & Infrastructure
\ view thread
I work for a small Water District and we are expanding our treatment plant, adding 4 new filters, upgrading pre-treatment as well as building new admin building and laboratories ($11 Million dollars is budgeted). We are trying to find some references that verify what a reasonable consulting engineering ...