Hi Todd, Assuming that the stream is not of high value, it may take 6 months to a year once you have Stream assessment, NEPA, and 50% design completed. It may be helpful to you if you can set up a pre-permitting field meeting with the agencies involved. The meeting outcome should provide a better ...
|