Assuming that the stream is not of high value, it may take 6 months to a year once you have Stream assessment, NEPA, and 50% design completed. It may be helpful to you if you can set up a pre-permitting field meeting with the agencies involved. The meeting outcome should provide a better idea.
------------------------------
Karuna Pujara M.ASCE
Vice President of Water Resources Discipline
ATCS, PLC
Herndon VA
------------------------------
Original Message:
Sent: 06-10-2024 12:00 PM
From: Todd Powell
Subject: Army corps permitting for portion of stream placement in box culvert
Does anyone have an estimate on the amount of time and money that would be required to obtain permitting through the Corps on placing 360 feet of stream in two 6' high x 9' wide box culvert? I attached a photo for the project that will be in Georgia.
------------------------------