Discussion: View Thread

  • 1.  Army corps permitting for portion of stream placement in box culvert

    Posted 21 days ago
    Edited by Tirza Austin 21 days ago
    Does anyone have an estimate on the amount of time and money that would be required to obtain permitting through the Corps on placing 360 feet of stream in two 6' high x 9' wide box culvert? I attached a photo for the project that will be in Georgia. 
    Photo of stream

     



    ------------------------------
    Todd Powell P.E., M.ASCE
    City Engineer
    City of Thomasville
    Thomasville GA
    ------------------------------



  • 2.  RE: Army corps permitting for portion of stream placement in box culvert

    Posted 15 days ago

    Hi Todd,

    Assuming that the stream is not of high value, it may take 6 months to a year once you have Stream assessment, NEPA, and 50% design completed.  It may be helpful to you if you can set up a pre-permitting field meeting with the agencies involved.  The meeting outcome should provide a better idea. 



    ------------------------------
    Karuna Pujara M.ASCE
    Vice President of Water Resources Discipline
    ATCS, PLC