As per ASCE 7-22 Section 7-22, all the pile caps are to be tied together with the foundation ties.
In the attachment, two types of pile cap and foundation tie system are shown as PLAN -A and PLAN-B
for a one-story structure having two spans transversely and 3 spans for longitudinally.
I think PLAN -A definitely meets the requirements of the section 12.13.7.2.
My question is whether PLAN-B is acceptable or not, which please advise.
Please also advise that the foundation ties may be omitted where reinforced concrete ground floor slab is
provided over the foundation system.
------------------------------