Professional and Career Topics

 View Only
Expand all | Collapse all

When is overdesign the correct design?

  • 1.  When is overdesign the correct design?

    Posted 06-12-2025 07:02 PM

    We all recognize that some level of overdesign is often necessary due to the many uncertainties inherent in whichever flavor of design process you are involved in -think sizing for peak flows, factoring in future loads, or building in safety margins. But overdesign isn't always about uncertainty. Sometimes it's driven by practicality. For example, a contractor might have materials on hand that exceed the spec, but using them avoids delays or otherwise reduces costs overall. Have you encountered other situations where overdesign was chosen for practicality rather than uncertainty? 

    I can go first:

    I was once asked to size a small pipe by a colleague. I asked another colleague to review my work, and explained that I was torn between pipes of two different sizes. My colleague reviewed my work and then simply said "either of these will probably meet the expected flow, but realistically anything less than the larger one is likely going to clog all the time". 



    ------------------------------
    Christopher Seigel P.E., M.ASCE
    Civil Engineer
    ------------------------------


  • 2.  RE: When is overdesign the correct design?

    Posted 06-13-2025 10:07 AM

    For me this is an every day thing. I work in house for a contractor and only running one case to meet scheduling demands, or simplify fabrication/installation is often a higher mandate than value engineering the materials costs. One of the bigger jobs I am working on right now involves steel tubes supported at their ends by embeds in the columns. Some of the steel has long spans with flood impact loading and some of it is a couple feet long and supporting nearly nothing; despite drastically different load cases, these use the same steel & embed detailing because it reduced a lot of timelines and cost despite the additional material. 



    ------------------------------
    Renn Henry, PE
    Staff Engineer
    ------------------------------



  • 3.  RE: When is overdesign the correct design?

    Posted 06-17-2025 05:00 PM

    Thanks Renn. Its always interesting getting to hear about how things work in your space, which is so different from my own.



    ------------------------------
    Christopher Seigel P.E., M.ASCE
    Civil Engineer
    ------------------------------



  • 4.  RE: When is overdesign the correct design?

    Posted 06-23-2025 11:36 AM

    This is a really important question, and I think that since we design to a code we think of additional capacity as "over" design.

    Because codes are a minimum, additional capacity is "right" design.  Not providing the extra capacity and having the pipes clog is a design failure, therefore following the code would be under designing the system.  Designing a hollow sidewalk for pedestrians in a location where a truck could drive on it meets the code for the sidewalk but is under designed for the likely load, even if the code does not mention it.

    On the other hand, sometimes additional capacity is not to avoid failure but to save time or money in design or labor.  But is this over design?  There is a case to be made that it is not since engineering also takes cost into account.  But others might see it differently.

    Thinking about these questions is what makes us better engineers and gives us flexibility in how we design and build our projects.



    ------------------------------
    Sarah Halsey P.E., M.ASCE
    New York NY
    ------------------------------



  • 5.  RE: When is overdesign the correct design?

    Posted 06-24-2025 10:32 AM

    Hi Sarah

    As a young engineer I made the mistake to leave too little margin in prelimimary dimensioning to accommodate additional loads emerging lateron.

    Only with professional experience I learned about the value of robustness that economic design often means to chose the same size for a group of members with similar degree of utilization for the ease of fabrication and guarding against confusion during assembly.

    As Professor Alain Harris at Imperial College stated: Shouldn't the sail-like concrete roof structure of the Sydney Opera House better have been designed with the same curvature in order to allow reuse of the shuttering?



    ------------------------------
    Joerg-Martin Hohberg D.I.C., MSc, Ph.D., Aff.M.ASCE
    Senior Consultant
    Bremgarten B. Bern
    ------------------------------



  • 6.  RE: When is overdesign the correct design?

    Posted 07-07-2025 03:08 PM

    Hi Joerg-Martin,

    I too tried to design too close to the limits.

    I also saw how critical it is to understand how reinforcing goes together and leave a little more space than is required by code when I was on site for a pour and the designer had left the absolute minimum spacing between the bars.



    ------------------------------
    Sarah Halsey P.E., M.ASCE
    New York NY
    ------------------------------



  • 7.  RE: When is overdesign the correct design?

    Posted 06-30-2025 12:27 PM

    The question might be,When is "Overdesign" Overdesign?



    ------------------------------
    Lewis Ewing P.E., M.ASCE
    Engineer
    Carollo Engineers PC
    Irvine CA
    ------------------------------



  • 8.  RE: When is overdesign the correct design?

    Posted 06-30-2025 12:28 PM

    Some overdesign is acceptable, but in my experience some engineers go overboard. Early in my career, I was the project manager for a 3-story underground concrete-framed garage which served as the base for three steel framed buildings: two were 6-stories and one was 12-stories.  The project managers for those structures provided steel columns to go through the concrete structure to the foundation.  They had similar bay spacings.  I noticed that the columns for one of the 6-story buildings were the same size as for the 12-story and much bigger than the other 6-story building. When I asked that project manager why, he said he never designed over 0.67 on the interaction equation (which code allows one to get to 1.0).  In my opinion, that was a waste of the client's money. 



    ------------------------------
    Colin Maynard P.E., S.E., M.ASCE
    Vice President
    Anchorage AK
    ------------------------------



  • 9.  RE: When is overdesign the correct design?

    Posted 06-30-2025 12:29 PM

    I once designed an upgrade of a one-mile length of urban state highway, starting with a two-lane highway having some right turn-lanes, and upgrading it to a 4-lane undivided highway with a shared center left turn-lane.  Near one terminus of the project, where the City boundary was, the 4-lane with shared center turn-lane began to transition down to 2 lanes (one-lane each direction).  The transition to 2-lane ended about 200 feet short of a T-intersection.  I decided to instead keep an extra right turn-lane going until it reached the side road, which T'd to the right.  The peer review questioned why I created the right turn lane, and considered it a wasteful extra expense.  I provided the following reasons:  1). while drivers are transitioning from 2 lanes in one direction, down to the one lane, they should not have to unsafely compete with other drivers intending to perform a right-turn within the same stretch of roadway; 2.) There was a standard design instruction that if a future development was expected to occur, the design could include some overdesign that would fit in with the future development.  My main reasoning was for reason number 1.  The future development reason (2.) -- to put it bluntly -- was mocked.  However, reason 1 was determined to be sufficient to proceed with the added right turn-lane.  A year or two after the project completion, a large chain-store corporation decided to construct a huge distribution center just past the end of the transition to 2 lanes, and the highway needed to be widened to a point past the new distribution center.  The turn-lane was a necessary part of that widening. 



    ------------------------------
    John Cline P.E., M.ASCE
    Engineer
    Macon MO
    ------------------------------



  • 10.  RE: When is overdesign the correct design?

    Posted 07-07-2025 11:38 AM

    I the over-design not an intentional modification of design codes/ practice and factors of safety based on an assessed risk by the designer? Should the codes not provide a basis for the assessment of risk in a particular situation and the modification of the design requirements.



    ------------------------------
    Stephen Leach C.Eng, M.ASCE
    Consultant Executive
    Luling LA
    ------------------------------



  • 11.  RE: When is overdesign the correct design?

    Posted 07-14-2025 11:12 AM

    Great topic Christopher. I wouldn't say overdesign is the correct design. It can rather be termed as the traditional or conventional method in design processes. One important reason for this – is the lack of surety or absolute confidence in design factors – the uncertainty. As an engineering project is perceived to ride on an upward trend in risk scale – so does the necessity of increasing the embedment of layers of redundancy (or Factor-of-Safety) in designs.

    In probabilistic concept of design – this method is known as the Level – 0 or deterministic design. On coastal engineering, here are something from Uncertainty Propagation in Wave Loadings:

    In engineering design processes, the traditional method of accounting for uncertainty is done simply by including some redundancy in the system – by the so-called factors of safety – conspicuously described and/or inconspicuously embedded in some practices (for example, using maximum load and minimum strength; and summation of different loads together although they may not occur simultaneously). Further elaboration on coastal design processes can be found in Oumeraci et al (1999), Burcharth (2003) and Pilarczyk (2003). They scaled the processes of design as: Level 0 – deterministic approach; Level I – quasi-probabilistic approach; Level II – approximate probabilistic approach; and Level III – fully probabilistic approach. In the Level 0 approach, parameter uncertainties are not accounted for, instead experience and professional judgment are relied upon to implant redundancy. This practice as a way of developing confidence or assurance – represents in reality – a process of introducing another layer of uncertainty – partly because of heuristics associated with judgments. Or in another interpretation, it amounts to over-designing structure elements at the expense of high cost. For the other three Levels, a load-strength reliability function is defined in different scales to account for parameter uncertainties.

    Dilip

    ---------

    Dr. Dilip K Barua, Ph.D

    Website Links and Profile






  • 12.  RE: When is overdesign the correct design?

    Posted 07-21-2025 11:18 AM

    Design structure eccentric it may work a lots of calculation has been done if even it's over design. Our human software could be doing well with the rest. 

    Alex Thomas MASCE FIE PE MIGS 

    Thudianplackal C/0 Bethel Koch Ernakulam Kerala India 



    ------------------------------
    Alex Thomas R.Eng, C.Eng, M.ASCE
    Senior Site Engineer
    Geo Structurals Pvt Ltd
    ErnakulamAlexThomasR.Eng, C.Eng, M.ASCEIndia
    ------------------------------



  • 13.  RE: When is overdesign the correct design?

    Posted 07-22-2025 01:17 PM

    Alex, if I have understood your comment correctly – it is about whether or not computation-intensive advanced design processes are worth to pursue – instead of following the well-established conventional deterministic design that comes with layers of redundancy.

    I was asked this type of question when my ISOPE paper: Wave Loads on Piles – Spectral Versus Monochromatic Approach was published in 2008 (also discussed in Wave Forces on Slender Structures). As you know, ocean waves are ubiquitously Spectral – yet, conventional design processes treat them Monochromatic.

    My answer to the question was ambiguous – partly because the case I presented showed that the monochromatic method underestimates the wave forces only by about 9%. For such a marginal error of similar cases – perhaps it is not worth to pursue the more computation-intensive advanced method.

    But, looking down the future – with AI taking over many of the design tasks gradually – one can say that advanced probabilistic or reliability design processes are likely to replace many conventional procedures.

    Dilip

    ---------

    Dr. Dilip K Barua, Ph.D

    Website Links and Profile






  • 14.  RE: When is overdesign the correct design?

    Posted 07-21-2025 11:17 AM

    Overdesign in structural systems is often necessary to achieve simplicity in construction. For instance, reducing the number of different section types can make the structure more economical to build and facilitate the procurement of materials. Overdesign may also be appropriate in contexts where material availability is limited, where serviceability limit states govern the design, or where durability and life-cycle requirements are critical.

    However, in seismic design, overdesign must be approached with caution. If not properly balanced, it can lead to torsional irregularities or unintended force concentrations under seismic loading. This is particularly relevant in steel structures designed to resist earthquakes, where overstrength, especially due to expected material strengths, can result in unintended load paths and local overstress. In such cases, careful evaluation of overdesign is essential to ensure that the seismic performance objectives are not compromised.



    ------------------------------
    [Olga] [Marin]
    [Tafur Marin Ingenieria Estructural SAS]
    [+57 3148944222]
    [Colombia]
    [olgalmarinc@...]
    ------------------------------



  • 15.  RE: When is overdesign the correct design?

    Posted 07-24-2025 01:24 PM

    When ductility matters, 6 #12 mm replaced by 4 #16 but it had it's on drawback. When 5 #20 replayed by 6 #16 it shows failure even than same alignment and patterns for beams and columns 

    Alex Thomas MASCE FIE PE 

    Thudianplackal C/0

    Bethel Koch Ernakulam Kerala India 



    ------------------------------
    Alex Thomas R.Eng, C.Eng, M.ASCE
    Senior Site Engineer
    Geo Structurals Pvt Ltd
    ErnakulamAlexThomasR.Eng, C.Eng, M.ASCEIndia
    ------------------------------



  • 16.  RE: When is overdesign the correct design?

    Posted 08-01-2025 10:00 AM

    As noted previously, simplicity is definitely a factor.  Which configuration is easiest to install?  Ductility is certainly a consideration as well.  More of a thinner material may be desirable.  Less is more for flexibility and failure of the material rather than fastener.



    ------------------------------
    Chad Morrison P.E., F.ASCE
    Professional Engineer
    Greenville RI
    ------------------------------



  • 17.  RE: When is overdesign the correct design?

    Posted 07-24-2025 02:42 PM

    Reading the comments reminds me that water-related design an be very different than structure-related design. It seems that water design is much less reliant on codes. Am I mistaken?



    ------------------------------
    William McAnally Ph.D., P.E., BC.CE, BC.NE, F.ASCE
    ENGINEER
    Columbus MS
    ------------------------------



  • 18.  RE: When is overdesign the correct design?

    Posted 07-25-2025 10:59 PM

    Bill – Mc, I don't think you are mistaken. As intuitively obvious as they are – there are many reasons why design processes – pose different problems depending on where they are sited. For example, river water-front, coastal water-front and in-water structural planning and designs – must be approached differently than their cousins in other areas.

    Appropriate and applicable Standards and Codes are always there irrespective of where the structure is located. An engineer cannot circumvent them.

    In terms of Coastal Civil Engineering (CCE) works – one needs to account for different Force Fields in a Coastal System that dictate appropriate design approaches. Further, hydrodynamic interactions with the structure – like the types of Wave Structure Interactions & Scour – must be accounted for.

    Here are what have been highlighted in the Civil Engineering on our Seashore:

    . . . Coastal structures are not like a tall building standing on a dry land – and they should not be treated as such. Because of their exposed location in water or at the water-front, they continuously come under attack by the dynamic and uncertain metocean forcing – from regular to extreme. They must withstand different aspects of the force fields - during construction and operational lifetime, as well as face the consequences of uncertain fluid-structure interaction processes, and have to cause minimum impacts on the surrounding environments.
    Therefore the role of a coastal engineer is very crucial – not only in the establishment of design and operational conditions and criteria, but also during the process of planning, design and construction. Lack of effective coordination, cooperation and concordance among various disciplines – or perhaps in not recognizing the proper roles required of certain disciplines – could lead to earning bad reputation, and to risks of incurring serious economic losses . . .



    Dilip
    ---------

    Dr. Dilip K Barua, Ph.D

    Website Links and Profile






  • 19.  RE: When is overdesign the correct design?

    Posted 07-28-2025 11:01 AM

    You are absolutely correct, Dilip, in noting a difference in the force fields that must be considered in water resources engineering. You have helped clarify my thinking in that regard and also in the matter of standards and codes for water resources.

    In some (many?) areas of water resources engineering, we have design manuals, such as the Georgia Stormwater Manual and Corps of Engineers Manuals that provide guidelines for design processes which seem more flexible than I perceive building codes to be. For example, guidelines on the length, angle, and spacing of riverine and coastal training structures are typically non-specific, giving the designer wide latitude to fit the design to the situation.

    Some countries, such as the UK, label guidelines similar to the Corps' as "British Standards," so perhaps there's less a distinction than I perceive.



    ------------------------------
    William McAnally Ph.D., P.E., BC.CE, BC.NE, F.ASCE
    ENGINEER
    Columbus MS
    ------------------------------



  • 20.  RE: When is overdesign the correct design?

    Posted 07-28-2025 11:01 AM

    I've been so engaged with separating water engineering from structural engineering that I've neglected to respond to your question, Chris.

    Overdesign is often the better answer. When I worked for a large consulting firm we sized the storm drains for planned development until the P.E. in charge noted that the owner had an additional 50 acres above the development. The owner admitted that he intended to extend the subdivision if Part 1 succeeded. So, we sized storm drains for the expanded subdivision. Larger drain lines cost more, of course, but much less than installing extra capacity later. The owner chose the overdesign.

    Bill Mc



    ------------------------------
    William McAnally Ph.D., P.E., BC.CE, BC.NE, F.ASCE
    ENGINEER
    Columbus MS
    ------------------------------